Process — RIBA stages 0 to 7, in plain English
Most people have never done this before. Here is exactly how it goes.
Seven stages, from a first conversation to living in the finished thing. For each one: what happens, how long it usually takes, what we need from you, and when you pay.
First conversation and brief
2–4 weeksA call, then a visit to the property. We measure up, take photographs and write down what you actually want, including the things you have not said out loud yet. You get a written brief, a realistic budget range and an honest view of planning risk.
Concept design
3–5 weeksTwo or three genuinely different options, drawn as plans and simple 3D views, so you can see the trade-offs rather than being sold one idea. We meet to talk them through and then develop the one you choose.
Planning application
8–12 weeksWe prepare and submit the drawings and statements the council needs, and handle their questions. Determination is usually eight weeks from validation, sometimes longer. We tell you the day it is decided.
Technical design
6–10 weeksThe package a builder can price and build from: construction details, specifications, and coordination with a structural engineer and building control. This is where a project either gets cheaper or gets expensive, so it is worth the time.
Tender and appointing a builder
4–6 weeksWe send the package to three or four contractors, compare their prices on a like-for-like basis and explain what the differences mean. You appoint the builder directly, under a proper contract.
On site
3–9 monthsSite visits at agreed intervals, answers to the builder’s questions, and monthly valuations so you only pay for work actually done. You get a short written note after every visit, so you always know where things stand.
Handover and after
OngoingCompletion certificates, warranties and a snagging list worked through with the builder. We come back after six months to see how the building is behaving and whether anything needs attention.